EVERSOURCE: WEST ROXBURY TO NEEDHAM RELIABILITY PROJECT
ELECTROMAGNETIC FIELD TESTING
Link to Reports of EMF testing and reviews
TOWN OF NEEDHAM PROJECT UPDATES & PHOTOS
Link to Eversource Project Weekly Updates and Photos
LINK TO EVERSOURCE WEBSITE PROJECT PAGE
West Roxbury to Needham Reliability Eversource Webpage
Eversource West Roxbury to Needham Reliability Project Update
Condition P Compliance Filing (PDF) August 7, 2020
Route with alignment (PDF) (where digging will be done) - Note: Please magnify these documents once opened to read the street detail.
Grant of Location Application (PDF) from Eversource for Noticed Alternative Route
Public Hearing to be held on Wednesday, June 13, 2018 7:30 p.m. Powers Hall in Town Hall
Town of Needham's Response to Opposition of NStar to the Town's Motion to Reopen Hearing, 1/24/2018
Town of Needham filed a Motion to Reopen Hearing to the Energy Facilities Siting Board (EFSB) dated 1/11/2018.
All documents regarding Eversource's petition to install the transmission line are available at the EFSV File Room by inserting the docket number: EFSB16-02.
Example of pre and post EMF Testing – Eversource
Manhole Locations Maps (PDF) South Street Route
Presentation Update (PDF) by Eversource to Board of Selectmen on November 14, 2017
Needham Board of Health Letter to Selectmen re: Health Impacts of Eversource West Roxbury to Needham Reliability Project, November 14, 2016.
After conducting a public hearing on April 26th and listening to comments and feedback from the community, the Board of Selectmen has expressed concern about the preferred route and its impact on walking neighborhoods. After deliberation on May 2nd, the Needham Board of Selectmen voted to recommend that Eversource and the Energy Facility Siting Board consider the Noticed Alternative Route ("the South Street Route") with variations that avoid the Valley Road neighborhood.
Notice of Public Hearing by Board of Selectmen, April 26, 2017 (PDF)
Routes proposed by Eversource (PDF)
Response by Eversource to Town's Second Set of Documents and Information Requests (PDF), March 10, 2017
Response by Eversource to Town's First Set of Documents and Information Requests (PDF), March 6, 2017
Siting Board's Revised Procedural Schedule (PDF), February 21, 2017
Second Set of Documents and Information Requests (PDF) submitted to Energy Facilities Siting Board Feb 24, 2017
First Set of Documents and Information Requests (PDF) submitted to Energy Facilities Siting Board Feb 24, 2017
Eversource Presentation on West Roxbury to Needham Reliability Project, January 23, 2017 (PDF)
Eversource: Analysis to Support Petitions Before the Energy Facilities Siting Board EFSB 16-02 (PDF)
West Roxbury to Needham Reliability Project - Volume 1 - Submitted to Energy Facilities Siting Board
Prepared by: Epsilon Associates, Inc. dated June 15, 2016
File is large, please be patient.
Prepared by: Gradient Corp for Epsilon Associates & Eversource, dated March 18, 2016
Eversource Project Update to Board of Selectmen, October 4, 2016 (PDF)
Commonwealth of Massachusetts, Energy Facilities Siting Board Public Comment Hearing, 9/27/16 (PDF)
Notice of Adjudication and Notice of Public Comment Hearing (for 9/27/16 hearing) (PDF)
Eversource Energy Presentation Update to the Board of Selectmen, 9/6/2016 (PDF)
Project Update and Comment Feedback Form (PDF)
Presentation to Board of Selectmen 3/8/2016 (PDF)
(Eversource plans for improving the reliability of the transmission lines between West Roxbury and Needham.)